Tue, Nov 17, 2026
Kitchen tile is underway
The porcelain you picked is going down in the kitchen. We expect the first section done by the end of the week, then we move toward the family room.
Demo prototype — fictional sample data. Changes stay in this browser tab and are not saved to a server.
Your project
1240 Alhambra Circle, Coral Gables, FL 33134
58% complete · target Jan 25
Permits approved
Sun, Aug 30, 2026
Tie beam & slab poured
Fri, Oct 9, 2026
Framing complete
Fri, Nov 6, 2026
Rough inspections
Mon, Nov 23, 2026
Drywall & insulation
Thu, Dec 10, 2026
Finishes & tile
Tue, Jan 5, 2027
Final walkthrough
Mon, Jan 25, 2027
Tue, Nov 17, 2026
The porcelain you picked is going down in the kitchen. We expect the first section done by the end of the week, then we move toward the family room.
Sat, Nov 7, 2026
The second floor is fully framed and sheathed. Next up: electrical, plumbing, and rough inspections.